{"@context":"https://schema.org","@type":"NewsArticle","mainEntityOfPage":"/carajas/cidades/maraba/832345/construcao-da-nova-ponte-avanca-com-52-estacas-concretadas","headline":"Construção da nova ponte avança com 52 estacas concretadas","datePublished":"2023-10-17T17:33:53-03:00","dateModified":"2023-10-17T18:56:53-03:00","author":{"@type":"Person","name":"Com informações Osvaldo Henriques/ Secom PMM","url":"/carajas/cidades/maraba/832345/construcao-da-nova-ponte-avanca-com-52-estacas-concretadas"},"image":"/img/Artigo-Destaque/830000/PONTE-OK_00832345_0_.jpg?xid=2754760","publisher":{"@type":"Organization","name":"DOL","url":"/","logo":"/themes/DOL/img/logoDOL.png","Point":{"@type":"Point","Type":"Customer ","telephone":"+55-91-98412-6477","email":"[email protected]"},"address":{"@type":"PostalAddress","streetAddress":"Rua Gaspar Viana, 773/7","addressLocality":"Belém","addressRegion":"PA","postalCode":"66053-090","addressCountry":"BR"}},"description":"A nova ponte sobre o Rio Itacaiúnas vai melhorar a mobilidade urbana em Marabá, no sudeste do estado","articleBody":"\\u0026lt;p\\u0026gt;A constru\\u0026#231;\\u0026#227;o da ponte sobre o rio Itacai\\u0026#250;nas entra em nova etapa e avan\\u0026#231;a na execu\\u0026#231;\\u0026#227;o da concretagem dos pilares, estacas e travessas. Na manh\\u0026#227; da \\u0026#250;ltima segunda-feira (16), os oper\\u0026#225;rios trabalhavam na coloca\\u0026#231;\\u0026#227;o das estruturas de ferro nos 20 pilares em constru\\u0026#231;\\u0026#227;o.\\u0026lt;/p\\u0026gt;\\u0026lt;p\\u0026gt;De acordo com o engenheiro civil Diego Garcez, do Cons\\u0026#243;rcio Ponte Itacai\\u0026#250;nas, formado pelas empresas Construtora A Gaspar S.A e Arteleste Constru\\u0026#231;\\u0026#245;es, j\\u0026#225; foram concretadas 52 estacas de 1200 mm em \\u0026#225;rea de terra firme e de 2000mm no leito do rio, das 64 que ser\\u0026#227;o montadas.\\u0026lt;/p\\u0026gt;\\u0026lt;p class=\\u0026quot;\\u0026quot;\\u0026gt;\\u0026amp;nbsp;\\r\\n\\t\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n \\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n \\u0026lt;figure class=\\u0026quot;dol-img-article\\u0026quot;\\u0026gt;\\r\\n \\r\\n \\r\\n \\r\\n \\r\\n \\u0026lt;img loading=\\u0026quot;lazy\\u0026quot; class=\\u0026quot;lozad desk\\u0026quot; alt=\\u0026quot;J\\u0026amp;#225; foram concretadas 52 estacas de 1200 mm em \\u0026amp;#225;rea de terra firme e de 2000mm no leito do rio\\u0026quot; data-src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-3_00832345_0_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-3_00832345_0_.jpg%3Fxid%3D2754763%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754763\\u0026quot; src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-3_00832345_0_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-3_00832345_0_.jpg%3Fxid%3D2754763%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754763\\u0026quot;\\u0026gt;\\r\\n\\r\\n \\r\\n \\u0026lt;figcaption\\u0026gt;\\r\\n \\u0026lt;span\\u0026gt;\\u0026#128247; J\\u0026amp;#225; foram concretadas 52 estacas de 1200 mm em \\u0026amp;#225;rea de terra firme e de 2000mm no leito do rio |\\u0026lt;/span\\u0026gt;\\u0026lt;strong\\u0026gt;S\\u0026amp;#233;rgio Barros\\u0026lt;/strong\\u0026gt;\\r\\n \\u0026lt;/figcaption\\u0026gt;\\r\\n \\u0026lt;/figure\\u0026gt;\\r\\n\\r\\n\\u0026amp;nbsp;\\u0026lt;/p\\u0026gt;\\u0026lt;p\\u0026gt;“Estamos na fase da concretagem dos blocos, pilares e travessas. J\\u0026#225; executamos a concretagem de 52 das 64 estacas previstas em projeto, 20 pilares e dois mastros do trecho estaiado, \\u0026#233; a etapa da execu\\u0026#231;\\u0026#227;o da infra e da superestrutura da ponte”, explicou o engenheiro civil, Diego Garc\\u0026#234;s, do Cons\\u0026#243;rcio Ponte do Itacai\\u0026#250;nas.\\u0026lt;br\\u0026gt;\\u0026lt;/p\\u0026gt;\\u0026lt;p\\u0026gt;Os pilares concentram-se na maior parte na margem esquerda do rio, no sentido ao n\\u0026#250;cleo da Cidade Nova, onde est\\u0026#227;o sendo erguidos os 20 pilares. O projeto prev\\u0026#234; ainda a constru\\u0026#231;\\u0026#227;o de mais quatro pilares na margem direita do rio e mais dois no leito do Itacai\\u0026#250;nas.\\u0026lt;/p\\u0026gt;\\u0026lt;p class=\\u0026quot;\\u0026quot;\\u0026gt;\\u0026amp;nbsp;\\r\\n\\t\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n \\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n \\u0026lt;figure class=\\u0026quot;dol-img-article\\u0026quot;\\u0026gt;\\r\\n \\r\\n \\r\\n \\r\\n \\r\\n \\u0026lt;img loading=\\u0026quot;lazy\\u0026quot; class=\\u0026quot;lozad desk\\u0026quot; alt=\\u0026quot;Previs\\u0026amp;#227;o \\u0026amp;#233; de que a ponte seja conclu\\u0026amp;#237;da no segundo semestre de 2024\\u0026quot; data-src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-2_00832345_1_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-2_00832345_1_.jpg%3Fxid%3D2754764%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754764\\u0026quot; src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-2_00832345_1_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-2_00832345_1_.jpg%3Fxid%3D2754764%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754764\\u0026quot;\\u0026gt;\\r\\n\\r\\n \\r\\n \\u0026lt;figcaption\\u0026gt;\\r\\n \\u0026lt;span\\u0026gt;\\u0026#128247; Previs\\u0026amp;#227;o \\u0026amp;#233; de que a ponte seja conclu\\u0026amp;#237;da no segundo semestre de 2024 |\\u0026lt;/span\\u0026gt;\\u0026lt;strong\\u0026gt;S\\u0026amp;#233;rgio Barros\\u0026lt;/strong\\u0026gt;\\r\\n \\u0026lt;/figcaption\\u0026gt;\\r\\n \\u0026lt;/figure\\u0026gt;\\r\\n\\r\\n\\u0026amp;nbsp;\\u0026lt;/p\\u0026gt;\\u0026lt;h2\\u0026gt;\\u0026lt;b\\u0026gt;VEJA COMO AS OBRAS AVAN\\u0026#199;AM\\u0026lt;/b\\u0026gt;\\u0026lt;/h2\\u0026gt;\\u0026lt;ul\\u0026gt;\\u0026lt;li\\u0026gt;ados seis meses desde o in\\u0026#237;cio da obra, j\\u0026#225; \\u0026#233; poss\\u0026#237;vel ver mudan\\u0026#231;as no cen\\u0026#225;rio de constru\\u0026#231;\\u0026#227;o da ponte com os pilares perfazendo o contorno do projeto. Em quatro dos pilares tamb\\u0026#233;m est\\u0026#227;o sendo colocadas as estruturas de ferro das travessas, que possibilitam ter a dimens\\u0026#227;o da largura das pistas de rolamentos.\\u0026lt;br\\u0026gt;\\u0026lt;/li\\u0026gt;\\u0026lt;li\\u0026gt;A nova ponte ter\\u0026#225; 524 metros de comprimento com 12 de largura, sendo 1,85 metros de faixa de eio. O prazo total para execu\\u0026#231;\\u0026#227;o do projeto, previsto no contrato, \\u0026#233; de 20 meses, sendo um m\\u0026#234;s para mobiliza\\u0026#231;\\u0026#227;o, 16 meses para a execu\\u0026#231;\\u0026#227;o da obra e tr\\u0026#234;s meses para os tr\\u0026#226;mites finais.\\u0026lt;/li\\u0026gt;\\u0026lt;/ul\\u0026gt;\\u0026lt;p class=\\u0026quot;\\u0026quot;\\u0026gt;\\u0026amp;nbsp;\\r\\n\\t\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n \\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n \\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n\\r\\n \\r\\n\\r\\n\\r\\n \\u0026lt;figure class=\\u0026quot;dol-img-article\\u0026quot;\\u0026gt;\\r\\n \\r\\n \\r\\n \\r\\n \\r\\n \\u0026lt;img loading=\\u0026quot;lazy\\u0026quot; class=\\u0026quot;lozad desk\\u0026quot; alt=\\u0026quot;A constru\\u0026amp;#231;\\u0026amp;#227;o da ponte sobre o rio Itacai\\u0026amp;#250;nas entra em nova etapa\\u0026quot; data-src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-1_00832345_2_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-1_00832345_2_.jpg%3Fxid%3D2754765%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754765\\u0026quot; src=\\u0026quot;https://cdn.dol-br.noticiasalagoanas.com/img/inline/830000/767x0/PONTE-OK-1_00832345_2_.webp?fallback=https%3A%2F%2Fcdn.dol-br.noticiasalagoanas.com%2Fimg%2Finline%2F830000%2FPONTE-OK-1_00832345_2_.jpg%3Fxid%3D2754765%26resize%3D380%252C200%26t%3D1748174354\\u0026amp;amp;xid=2754765\\u0026quot;\\u0026gt;\\r\\n\\r\\n \\r\\n \\u0026lt;figcaption\\u0026gt;\\r\\n \\u0026lt;span\\u0026gt;\\u0026#128247; A constru\\u0026amp;#231;\\u0026amp;#227;o da ponte sobre o rio Itacai\\u0026amp;#250;nas entra em nova etapa |\\u0026lt;/span\\u0026gt;\\u0026lt;strong\\u0026gt;Sara Lopes\\u0026lt;/strong\\u0026gt;\\r\\n \\u0026lt;/figcaption\\u0026gt;\\r\\n \\u0026lt;/figure\\u0026gt;\\r\\n\\r\\n\\u0026amp;nbsp;\\u0026lt;/p\\u0026gt;\\u0026lt;p\\u0026gt;A soma total da constru\\u0026#231;\\u0026#227;o da nova ponte est\\u0026#225; or\\u0026#231;ada em R$ 109 milh\\u0026#245;es. Deste total, R$ 50 milh\\u0026#245;es ser\\u0026#225; o aporte financeiro do Governo do Estado do Par\\u0026#225;, onde 50% desse valor j\\u0026#225; foi transferido e depositado.\\u0026lt;br\\u0026gt;\\u0026lt;/p\\u0026gt;\\u0026lt;h2\\u0026gt;\\u0026lt;b\\u0026gt;CONTE\\u0026#218;DO RELACIONADO:\\u0026lt;/b\\u0026gt;\\u0026lt;/h2\\u0026gt;\\u0026lt;ul\\u0026gt;\\u0026lt;li\\u0026gt;\\u0026lt;a href=\\u0026quot;/carajas/cidades/maraba/828941/manutencao-na-ponte-sobre-o-tocantins-continua-ate-o-dia-6?d=1\\u0026quot;\\u0026gt;Manuten\\u0026#231;\\u0026#227;o na ponte sobre o Tocantins continua at\\u0026#233; o dia 6\\u0026lt;/a\\u0026gt;\\u0026lt;/li\\u0026gt;\\u0026lt;li\\u0026gt;\\u0026lt;a href=\\u0026quot;/carajas/cidades/maraba/816954/iniciada-a-construcao-das-fundacoes-da-nova-ponte-em-maraba?d=1\\u0026quot;\\u0026gt;Iniciada a constru\\u0026#231;\\u0026#227;o das funda\\u0026#231;\\u0026#245;es da nova ponte em Marab\\u0026#225;\\u0026lt;/a\\u0026gt;\\u0026lt;/li\\u0026gt;\\u0026lt;/ul\\u0026gt;\\u0026lt;p\\u0026gt;A Prefeitura de Marab\\u0026#225; caber\\u0026#225; a manuten\\u0026#231;\\u0026#227;o das demais despesas, R$ 59 milh\\u0026#245;es, destinados para a constru\\u0026#231;\\u0026#227;o da ponte, como tamb\\u0026#233;m os servi\\u0026#231;os de infraestrutura nas vias de o at\\u0026#233; a cabeceira da ponte nas duas margens do rio.\\u0026lt;/p\\u0026gt;\\u0026lt;p\\u0026gt;“\\u0026#201; uma obra para o futuro e temos que pensar no tr\\u0026#226;nsito com maior fluidez e, hoje, j\\u0026#225; existe uma reclama\\u0026#231;\\u0026#227;o grande no tr\\u0026#226;nsito, mas temos que planejar a cidade para o futuro”, comentou F\\u0026#225;bio Moreira, secret\\u0026#225;rio municipal de via\\u0026#231;\\u0026#227;o e obras p\\u0026#250;blicas.\\u0026lt;/p\\u0026gt;\\u0026lt;div\\u0026gt;\\u0026lt;br\\u0026gt;\\u0026lt;/div\\u0026gt;","keywords":"construção da nova ponte sobre o rio itacaiúnas, construção da terceira ponte do itacaiúnas, construção de nova ponte em marabá"}
plus
plus

Edição do dia

Leia a edição completa grátis
Edição do Dia
Previsão do Tempo 27°
cotação atual R$


home
RIO ITACAIÚNAS

Construção da nova ponte avança com 52 estacas concretadas

A nova ponte sobre o Rio Itacaiúnas vai melhorar a mobilidade urbana em Marabá, no sudeste do estado

twitter Google News
Imagem ilustrativa da notícia Construção da nova ponte avança com 52 estacas concretadas camera Obras da nova ponte sobre o rio Itacaiúnas avançam em Marabá | Sérgio Barros

A construção da ponte sobre o rio Itacaiúnas entra em nova etapa e avança na execução da concretagem dos pilares, estacas e travessas. Na manhã da última segunda-feira (16), os operários trabalhavam na colocação das estruturas de ferro nos 20 pilares em construção.

De acordo com o engenheiro civil Diego Garcez, do Consórcio Ponte Itacaiúnas, formado pelas empresas Construtora A Gaspar S.A e Arteleste Construções, já foram concretadas 52 estacas de 1200 mm em área de terra firme e de 2000mm no leito do rio, das 64 que serão montadas.

Já foram concretadas 52 estacas de 1200 mm em área de terra firme e de 2000mm no leito do rio
📷 Já foram concretadas 52 estacas de 1200 mm em área de terra firme e de 2000mm no leito do rio |Sérgio Barros

“Estamos na fase da concretagem dos blocos, pilares e travessas. Já executamos a concretagem de 52 das 64 estacas previstas em projeto, 20 pilares e dois mastros do trecho estaiado, é a etapa da execução da infra e da superestrutura da ponte”, explicou o engenheiro civil, Diego Garcês, do Consórcio Ponte do Itacaiúnas.

Os pilares concentram-se na maior parte na margem esquerda do rio, no sentido ao núcleo da Cidade Nova, onde estão sendo erguidos os 20 pilares. O projeto prevê ainda a construção de mais quatro pilares na margem direita do rio e mais dois no leito do Itacaiúnas.

Previsão é de que a ponte seja concluída no segundo semestre de 2024
📷 Previsão é de que a ponte seja concluída no segundo semestre de 2024 |Sérgio Barros

VEJA COMO AS OBRAS AVANÇAM

  • ados seis meses desde o início da obra, já é possível ver mudanças no cenário de construção da ponte com os pilares perfazendo o contorno do projeto. Em quatro dos pilares também estão sendo colocadas as estruturas de ferro das travessas, que possibilitam ter a dimensão da largura das pistas de rolamentos.
  • A nova ponte terá 524 metros de comprimento com 12 de largura, sendo 1,85 metros de faixa de eio. O prazo total para execução do projeto, previsto no contrato, é de 20 meses, sendo um mês para mobilização, 16 meses para a execução da obra e três meses para os trâmites finais.
A construção da ponte sobre o rio Itacaiúnas entra em nova etapa
📷 A construção da ponte sobre o rio Itacaiúnas entra em nova etapa |Sara Lopes

A soma total da construção da nova ponte está orçada em R$ 109 milhões. Deste total, R$ 50 milhões será o aporte financeiro do Governo do Estado do Pará, onde 50% desse valor já foi transferido e depositado.

CONTEÚDO RELACIONADO:

A Prefeitura de Marabá caberá a manutenção das demais despesas, R$ 59 milhões, destinados para a construção da ponte, como também os serviços de infraestrutura nas vias de o até a cabeceira da ponte nas duas margens do rio.

“É uma obra para o futuro e temos que pensar no trânsito com maior fluidez e, hoje, já existe uma reclamação grande no trânsito, mas temos que planejar a cidade para o futuro”, comentou Fábio Moreira, secretário municipal de viação e obras públicas.

VEM SEGUIR OS CANAIS DO DOL!

Seja sempre o primeiro a ficar bem informado, entre no nosso canal de notícias no WhatsApp e Telegram. Para mais informações sobre os canais do WhatsApp e seguir outros canais do DOL. e: dol-br.noticiasalagoanas.com/n/828815.

tags

Quer receber mais notícias como essa?

Cadastre seu email e comece o dia com as notícias selecionadas pelo nosso editor

Conteúdo Relacionado

0 Comentário(s)

plus

    Mais em Marabá

    Leia mais notícias de Marabá. Clique aqui!

    Últimas Notícias